"How long does it take to build an app?" gets two very different answers online: one to three months, or four to six, sometimes much more. Both can be right. This guide explains the gap, gives a time per feature, and lays out an eight week MVP plan. The figures are RespireSoft's judgment unless we name a source, and third party pages were opened on 4 November 2026.
Why sources disagree
We looked at two guides. Netguru, seen on 4 November 2026, gives three tiers: an ideal MVP in 3 to 4 months, a foundational MVP in 6 to 12 months and a complex one in 12 to 24 months. Affective, seen on 4 November 2026, says "6 weeks to 6 months" overall and 8 to 16 weeks as typical, with a simple utility app at 4 to 8 weeks and a complex marketplace at 24 to 32. It also adds a 20 to 30 percent buffer for delays.
Three things explain the spread:
- What counts as an MVP. One team means a single journey, another means a product ready to sell.
- What is included. Some figures stop at code complete. Others include design, testing and store release.
- How many platforms. Affective says building for iOS and Android together adds 30 to 50 percent. A shared codebase with Flutter or Capacitor shrinks that.
Both pages are agency blogs, so the numbers are rough and partly sales material.
Time per feature
This table is RespireSoft's judgment for one small team, in working weeks for a feature on one shared codebase, including tests. Add time if it is your first project with us or your data is messy.
| Feature | Typical time | What stretches it |
|---|---|---|
| Sign in (email, social, reset) | 1 week | Single sign on, two factor, old user data to import |
| Payments | 1 to 2 weeks | Subscriptions, refunds, tax, a provider that must approve your account |
| Offline sync | 2 to 4 weeks | Conflicts when two devices edit the same record |
| Chat | 2 to 3 weeks | Attachments, read receipts, push, moderation |
| Maps and location | 1 to 2 weeks | Live tracking, routing, background location rules |
| Admin panel | 2 to 3 weeks | Roles, reports, exports |
| Store release | 1 to 2 weeks | Review rounds, privacy forms, screenshots, first release paperwork |
Features overlap, so the total is less than the sum, but not by much. Offline sync is the one most people underestimate, because the hard part is not storing data on the phone but deciding what happens when two devices change the same record while offline. Decide that rule on paper before any code is written, and the estimate becomes far more reliable. The same goes for payments: ask early which provider you will use and whether it needs to approve your business first.
A week by week plan for an eight week MVP
This plan assumes one main journey, one shared codebase, content ready at kickoff and a decision maker who answers within a day.
- Week 1. Scope, user journey, wireframes and accounts for stores, payments and email.
- Week 2. Visual design for the main screens, project set up, sign in.
- Week 3. The first half of the main journey, built on real data.
- Week 4. The second half, plus the first demo you can tap through.
- Week 5. Payments or the one integration the product depends on.
- Week 6. Admin panel, notifications and the edges: empty states, errors, slow networks.
- Week 7. Testing on real phones, fixes, store pages, privacy answers, reviewer notes and a demo account.
- Week 8. Submit to both stores, fix what review finds, launch.
It is tight on purpose. Anything not in the main journey waits for version two. If you want to see how we scope a first version, read about MVP development.
What delays a project
- Slow decisions. A week waiting for a yes costs more than a week of coding. Affective names slow approvals as a delay cause too.
- Missing content. Texts, product photos, price lists and legal pages arrive late far more often than code does.
- Third party accounts. Developer accounts, payment provider approvals, map keys and domain checks each take days, and some need a company document.
- Scope creep. "One more feature" is the most common cause both of the pages above give.
- Store review. Rules are not negotiable and timing is not ours. A first release often needs a second round.
- Platform quirks. Some phone models and operating system versions need extra fixes.
How to shorten it
- Cut the scope first. Remove half the features and ship; learn what people use.
- Start the accounts in week one. Apple, Google, payments and email can run in the background.
- Hand over content early. Put one person in charge of texts, images and approvals.
- Use one codebase. Flutter or Capacitor avoids a second build for the other platform.
- Ask for a demo every week. Small corrections now beat a large rewrite later.
- Prepare for review. Reviewer notes and a demo account prevent avoidable rejections.
To put a price next to the time, use the software cost calculator and read our custom software cost guide. When you have a scope, contact us and we will answer with our own estimate.
How we got these numbers
The time per feature table and the eight week plan are RespireSoft's judgment, drawn from projects we have built, and are not measured averages. Third party figures come from Netguru and Affective, both seen on 4 November 2026. Both are agency blogs, and Affective's own pages differ on the simple app figure, so treat them as rough. We invented no customer figures.